T-3
The clock is ticking now--we can no longer say
"We'll do that next week!"
It's down to days and hours...
Mike Deane was here at 6:30 am...
the last painter left at 7:45 pm!!
On site today:
Sherry and SY
Kyle Vigano - weeding, mowing, carpenter's assistant, hauling debris, running errands, "being available"
Kevin Kennedy - last minute carpentry at Carriage House; final install of "courting benches" in the Parterre Garden
Chris & Todd - Kennedy Electric, final trim work at the Carriage House--all lights are on!!!!
Paul Vencil & Chris - water is running (where it is supposed to!!) and the toilet works!
Painters - continuing with their punch list seeming to grow by the day
Patsy and Lewis - doing the work of 4-5 people planting, edging, mulching etc. all over the estate
Jessica Beverage - cleaning the fish pond; introducing a new clientele of fish!!!
Kyle Lundgren - installing cobblestone pad at Studio deck
Curtis Htg. & Cooling - closing in on completing the new HVAC system
Piedmont Mowers - maybe our final mowing!?
Patsy's creations! 1 |
Patsy's creations 2 |
New outdoor portable flooring system |
Fish pond overhaul - and new little fishes!!!! |
Let there be light at the new Carriage House |