Friday, July 26, 2013

Friday 07.26.2013

We have had a very productive week at Ramsay.
For the work week M-F, a cumulative total of 
56 people worked at the estate with well over
 300 man-hours of service and labor contributed.
We are all grateful for the work and the opportunity 
to contribute to the care, maintenance and improvementof this
 National Treasure called Ramsay.


On site today:

SY - the usual, with an extra dose of mediation thrown in for good measure--all part of the job!
Richard King - our part-time handy/yard man who we've mentioned for a couple of weeks.
We just got around to taking his picture this morning. Richard has lived in C'ville for a good while,
and is currently a part-time student at PVCC.

 
Richard now includes "painter" on his resume!




Kyle & the Masons - after some unintentional miscues
 between the "architect's plans" and the "desired outcome"
 we're back to "circle" one at the ellipse north of the Parterre
 garden. And all is well!






Kevin & Mike - making slow but steady progress with the
application of the Ipe deck  material--one of the strongest woods in
the world, harvested in South America.